Metering Installation Timeframes

These metering installation timeframes are for customers in New South Wales, South Australia, the Australian Capital Territory and Queensland.

Getting your electricity connected or making changes to your electricity connection can be a challenging process. At Powerclub we will work towards providing you with a smooth transition.

Give us a call on 1300 294 459 to discuss your meter needs with one of our specialists.

Where we need to arrange for a third party to complete the metering or connection work, we will coordinate this directly with them.

Timeframes for rectifying metering malfunctions

  • for a small customer - as soon as practicable and no later than 15 business days after they have been notified of malfunction
  • for type 1-3 metering installations - as soon as practicable and no later than two business days after notified of the malfunction
  • for all other metering installations - as soon as practicable and no later than 10 business days after being notified of the malfunction